Late-afternoon light on live oaks and November grass beside a quiet road curving into coastal Georgia woodland.

What Has to Happen Before Wild Heron Landing Gets Built in Georgetown

November 19, 2026

What sets the pace for Georgetown's next large group of new homes? Two pieces of road on Wild Heron Road. The zoning was settled in December 2023, and the city confirmed utility capacity in October 2026. Under an agreement Savannah City Council approved on August 13, 2026, the city will not release building permits for the Wild Heron Landing subdivision phase until Chatham County's roadway improvements are complete and the county accepts them.

For buyers weighing Savannah's southside, and for owners on the streets around King George Boulevard and Chevis Road, that order matters more than any sale date on a marketing page.

The land, and why it took four years to reach this point

The site is called the Fawcett Tract. It covers 227 acres of former farmland on the south side of Wild Heron Road, between King George Boulevard and Chevis Road, and Savannah annexed it in 2005. About 105 of those acres were rezoned for housing. City planning records describe the surrounding pattern as the Georgetown and Southern Woods neighborhoods, with townhome communities such as Wild Heron Villas and Trellis Way, and rural lots of two acres or more to the west.

Each step in the public record narrowed what could be built and attached another condition to the roads:

  1. May 17, 2022. The first concept plan showed 400 units on a mix of 40-foot and 50-foot lots.
  2. January 25, 2023. After meetings with residents, the plan was revised. Units were capped at 350, lots had to be at least 50 by 120 feet, a 40-foot strip was dedicated to Chatham County for future widening of Wild Heron Road, and the developer agreed to fund part of the Wild Heron and King George intersection work.
  3. May 2, 2023. The Planning Commission recommended approval with those conditions and a 6-foot HOA-maintained fence along the Wild Heron Road frontage.
  4. May 22, 2023. A third concept plan, shared with residents, carried those conditions plus the HOA-maintained privacy fence.
  5. December 19, 2023. City Council approved the rezoning 6 to 3. Savannah Morning News reported the plan at about 250 single-family lots and about 100 townhomes.
  6. August 13, 2026. Council unanimously approved the roadway MOU among the City of Savannah, Chatham County and Landmark 24 Homes.
  7. October 8, 2026. Council unanimously approved a water and sewer agreement for the tract.

The rezoning did not settle the road question. It set up a three-way negotiation that took until the summer of 2026 to finish.

Who pays for the intersection changed

In 2023, the plan was for the developer, the City of Savannah and Chatham County to each cover one-third of the Wild Heron Road and King George Boulevard intersection improvement. The city's rezoning agenda item estimated that work at $750,000. At the time, District 6 County Commissioner Aaron Whitely told the Savannah Morning News that the county would not commit to an even split until it understood the improvements in more detail.

By July 2026 the design had become two specific pieces. WSAV reported on a town hall where county engineers described a restricted crossing U-turn, or RCUT, at King George Boulevard and a roundabout at Wild Heron Road and Cherry Field Lane, with commissioners saying the developers would pay for the changes. Jake Henery, development services manager with the Chatham County Department of Engineering, explained the problem the RCUT is meant to fix:

"One of the issues particularly is from King George Boulevard onto Wild Heron, folks that make a left turn tend to back up traffic. This helps move traffic away along to the west of King George onto Wild Heron."

The August MOU put that arrangement in writing. The council agenda item describes the developer's obligation to build the roundabout and the RCUT, along with permitting and construction timelines, building-permit conditions, inspection, warranty, and eventual county ownership and maintenance of the roads. The financial impact to the city is listed as $0.

The builder now carries the cost of the roads, and it cannot get a single house permit in that phase until the roads pass county acceptance. City Manager Jay Melder made the same point to WSAV: developers are accountable for putting the traffic improvements in before the housing, and the city controls the housing permits.

The home count depends on which document you read

Anyone tracking how many homes are coming to Wild Heron Road will find three different numbers in the public record:

Source Date What it describes
Rezoning conditions Dec. 19, 2023 Maximum of 350 units, about 250 single-family lots and about 100 townhomes
WSAV town hall report July 8, 2026 200 single-family homes and 100 townhomes
Water and sewer agreement Oct. 8, 2026 352 single-family homes, served as 352 equivalent residential units

For planning purposes, the 2023 rezoning conditions set the ceiling at 350 dwelling units. The utility agreement is a capacity document, and it is written in equivalent residential units. The October agreement also names a different developer entity, GT Developers of Savannah, LLC, while the August MOU names Landmark 24 Homes. For a nearby owner, the useful takeaway is the scale. This is a few hundred homes on lots of at least 6,000 square feet, which is a substantial addition to one stretch of Wild Heron Road.

Water and sewer capacity and connection fees

The October 8 agreement says the water and sewer systems have adequate capacity for the development. It sets a connection fee of $1,387,232, which the developer pays before water meters are released "as each house goes online."

The market those homes will meet

The most recent figures from Savannah Area REALTORS cover September 2026 for the wider Savannah area, not Georgetown alone. They show median sales price up 1.8%, inventory up 16.2%, new listings up 6.6%, closed sales down 15.9%, percent of list price received down 0.2%, and days on market up 27.5%.

Taken together, that describes a fall 2026 market where buyers have more homes to choose from and more time to decide, while prices are holding roughly level. The September trend suggests competition for buyers will be real.

Some of that competition is already on the southside under the same builder name. As of mid-November, Landmark 24 Homes is marketing The Cove at Bradley Point South at 2 Dunnoman Drive in the 31419 ZIP code, reached from Highway 204 off Highway 17, with listed prices starting at $309,250. Its Sweetwater Station community, also in 31419, is listed in closeout. Builder pages change often, so treat those figures as a snapshot and check them again before relying on them. For a broader look at that tradeoff, our guide on new construction versus resale covers the general decision, and the comparison works the same way in Georgetown.

Using the sequence in a decision

  • If you're shopping resale near Wild Heron Road: The approved road plan describes an RCUT at King George Boulevard and a roundabout at Cherry Field Lane. Drive both locations at commute hours so you know how your route will change, and compare that against the Georgetown neighborhood page.
  • If you own nearby and are thinking about selling: A home valuation based on the September 2026 conditions is a better starting point than any guess about when the subdivision opens.
  • If you want to buy in Wild Heron Landing itself: Watch for the road improvements to be completed and accepted by Chatham County. Under the August MOU, that acceptance comes before building permits for the subdivision phase.

Weekends around here look different from the weekday traffic on King George Boulevard, and our look at Ogeechee Road on a Saturday covers that side of Georgetown.

If you're weighing a home near Wild Heron Road against the new construction coming behind it, Trophy Point Realty Group can help you line up road timing, resale options and your report date so you can decide with a full picture. Get a Free PCS & Relocation Consultation and we'll work through the Georgetown plan with you.